An ATS specification: 12 items a project cannot pass without

Most transfer-switch specifications read the same way: "400 A ATS, open transition, IP54". That is not enough — a contractor is free to supply any switch that matches the text, including one with no event log and no frequency monitoring. Below are the 12 items that need real numbers, with typical values to start from.

1. What the specification must contain

#ItemWhat to state
1Rated current and pole countCurrent from the load calculation with margin; 2, 3 or 4 poles; for four-pole, switched or solid neutral
2Short-circuit withstandThe value stated together with fuse type and rating — not on its own
3Transfer typeOpen, delayed (and its range), closed transition, bypass
4Voltage and frequencyFor example 400 V, 50 Hz; both values for dual-voltage schemes
5Voltage settingsMains trip threshold and return threshold, with time delays
6Frequency settingsSeparately for mains and generator — they are not symmetric
7Enclosure rating and locationIP32 indoors or IP54 outdoors; ambient temperature
8Control voltage12 or 24 V from the generator battery, or a separate source
9Controller functionsEvent log and its depth, real-time clock, number of start attempts, test timer
10Signals to monitoringDry contacts or a protocol (Modbus, SCADA), with the list of states transmitted
11InterlocksMechanical and electrical, preventing parallel operation of mains and generator
12Tests and documentationFactory test report, data sheet, manual in the project language, on-site load test

2. Switch rating: calculated, not copied from the generator

The rating follows the design load current at 400 V three-phase: I = S ÷ (√3 × U). Round up to the next standard rating, then check it against the short-circuit withstand — in that order.

Generator rating, kVACurrent at 400 V, ANext ATS rating, A
304363
5072100
100144160
150217250
200289350
250361400
320462500
400577630
500722800
6309091000
80011551250
100014431600
125018042000

Two caveats. First, if the switch carries the whole facility load when running on mains, the rating follows that load, not the generator — otherwise the switch is weaker than the supply. Second, with two generators in parallel the current through the switch is the sum, not the rating of one machine.

3. Short-circuit withstand: a number without a fuse means nothing

This is the item most often filled in wrongly. The published withstand applies only with a current-limiting fuse of the stated size; the switch alone was not tested at that current. The specification therefore states the pair.

Switch rating, AWithstand at 480 V with fuseFuse
40–12526 kAup to 125 A
160–25038 kAup to 250 A
350–50050 kAup to 500 A
630–80055 kAup to 800 A
1000–125065 kAup to 1250 A
1600–2000120 kAup to 3000 A

Values are per Cummins for a 480 V system. At 400 V the reference point is the fault level calculated at the switchboard, not a catalogue figure: the withstand in amperes stays the same, but it must be checked against the value for your scheme.

4. Settings: state numbers, not "standard"

A controller whose range is narrower than required has to be replaced, and it is better to learn that before purchase. The values below are typical, from Cummins specification SG-1478j for GTEC; ranges differ between manufacturers, the structure does not.

ParameterMainsGenerator
Voltage pickup80–95%, adjustable90%
Voltage dropout70–90%, adjustable75%
Overvoltage120% / 125%, all phases—
UnderfrequencyOff by default; 80% / 70%90% / 85%
Voltage sensingAll phasesOne phase

A specification wording that can be checked: "trip from mains when voltage falls below 85% for more than 2 s; return when above 92% for 3 min; start the generator 1 s after the trip". "Standard settings" cannot be checked.

5. Reading the model code

Where the project uses Cummins switches, the code is built on the GTEC matrix and fixes exactly what is usually lost in correspondence. Example: G T 3 0500 J N 5 2 A 000.

PositionMeaningOptions
1Product typeG — transfer switch
2Transfer typeT — open or delayed transition
3Poles2, 3, 4
4Rated current0063, 0100, 0125, 0160, 0200, 0225, 0250, 0350, 0400, 0500, 0630, 0800, 1000, 1250
5Voltage codeI — 220 V, J — 230 V, N — 220/380 V, O — 230/400 V, Q — 255/440 V, and others per the table
6Control typeN — 12 V, Q — 24 V (line-to-neutral); L — 12 V, P — 24 V (line-to-line)
7Frequency5 — 50 Hz, 6 — 60 Hz, 7 — 50/60 Hz
8Construction2 — IP32, K — assembly kit
9–10Revision and spec numberAssigned by the factory

The practical value: the code pins down control voltage and voltage code, the two characters most often lost in email. One wrong character gives a switch that will not start the generator from its own battery.

6. Three mistakes that recur

  1. "No-break" instead of "open transition". The Russian translation of Cummins manual 914-0100G-13 says "no-break transfer switch GTEC" on the cover, although GTEC is an open-transition device. It is a translation error, and it propagates through project documents. Check the specification, not the cover.
  2. One rating for everything. The switch is sized on generator output while it also carries the facility load on mains — where the current is higher, so the switch runs overloaded.
  3. Event log "later". The controller level is chosen on price, and a year on nobody can establish why the facility went dark: no log, no clock, only LEDs.

7. What to check at acceptance

  • Factory test report and data sheet in the project language — before installation, not after.
  • Nameplate code matching the design: poles, current, voltage, frequency, control voltage.
  • Presence and type of the fuses the withstand rating depends on.
  • Actual settings after commissioning — a printout or a photo of the screen, not a verbal assurance.
  • On-load transfer test: at least three cycles, with the voltage dip recorded.
  • Interlock test: manual closing of the second source while the first is closed must be impossible.
  • Signal-by-signal check of every state sent to monitoring.

FAQ

Can an ATS be installed without fuses?

Physically yes, but the published short-circuit withstand no longer applies: the switch was tested only together with a current-limiting fuse of the stated size. The specification states the pair.

What rating is needed for a 200 kVA generator?

The current at 400 V is about 289 A, so the next standard rating is 350 A. If the switch also carries the facility load on mains, the rating follows that load instead.

Is a four-pole ATS needed?

It depends on the earthing system. A four-pole switch with switched neutral is needed where the generator neutral must not be bonded to the mains neutral. The designer decides from the earthing scheme, and the specification must state it explicitly.

What matters more — transfer type or controller level?

They answer different questions. Transfer type decides what happens to the load during the transfer. Controller level decides what you will know about why the transfer happened. Continuous process needs both; an office standby needs open transition and a simple controller.