UPS and genset: sizing a generator for a UPS without nasty surprises

A UPS gives minutes of runtime, a genset gives hours and days. But together they do not always cooperate: the genset's voltage and frequency drift, and a UPS rectifier loads it differently from an ordinary load. Here is how to size the genset for a UPS and what to check before the first start.

1. What happens when the mains fails

  1. The mains is lost: an online UPS goes to battery with no break.
  2. Automation starts the genset and it reaches voltage and frequency within seconds.
  3. The ATS moves the UPS input to the genset (see transfer switches and genset automation).
  4. The UPS rectifier takes load gradually ("walk-in"), then battery recharge is added.
  5. After the mains returns, the load is transferred back after a delay.

The weak points at each step: a battery not sized for the start time, a genset that has not settled, load applied in one hit, and recharge power not counted.

2. How to size the genset

Do not size from the UPS output rating. The input power is higher: UPS losses plus battery recharge. By Reddy Generators material:

UPS input kW = output kW ÷ efficiency + charging kW; genset kVA ≥ input kW ÷ input power factor × harmonic margin + other loads.

An illustrative example from the same source: a 40 kW UPS at 0.94 efficiency → 42.6 kW; about 5 kW recharge → 47.6 kW; at a power factor near 0.85 (six-pulse rectifier without filter) that is about 56 kVA; with a 1.5–2 margin, 84–112 kVA for the UPS alone, plus lighting and air conditioning of the UPS room.

3. Margin by rectifier type

UPS input typePractice
Older thyristor, 6-pulseCaterpillar: standby set at least 1.6 × the UPS input kW
Thyristor, 12-pulseCaterpillar: at least 1.4 ×
Modern IGBT with power-factor correction (PFC)Makers state power factor ≥ 0.99 and THDi around 3 % or less; one supplier estimates the genset can be about 1:1 to input power plus recharge

A UPS supplier's account of Cummins manual T-030 notes that UPS makers once asked for a genset two to five times the UPS rating, and that it is now more cost-effective to require a UPS compatible with the genset than to oversize the genset. General rules quoted by makers: Eaton suggests, for UPS of 20 kVA and above, a genset of at least 1.5 × the UPS output kW, and 2 × for 20 kVA and below; for UPS up to 25 kW Eaton gives multipliers on the total load (UPS, air conditioning and other equipment): 2 × for natural-gas and mechanical-governor sets and 1.5 × for diesel and electronic-governor sets. UPS maker AEC prints a general rule of 1.5 × input power in its manuals, which covers recharge with margin.

These numbers do not replace written guidance from the UPS and genset makers: take the factor from the manufacturer of your model.

4. Matching voltage and frequency

  • UPS input window. Every UPS has input voltage and frequency limits. If the genset leaves them, the UPS treats the source as unstable and stays on battery. By Eaton, staying on battery permanently will eventually run the battery down and drop the load.
  • Rate of frequency change. In Cummins T-030 (as relayed by a supplier) static UPS are listed as loads sensitive to frequency changing faster than 0.5 Hz per second. Check that the genset does not hunt faster than the UPS tolerates after load steps.
  • Gas gensets respond more slowly to load steps, so general guidance sizes them larger. See the articles on Jenbacher and Caterpillar G3500.
  • Bypass synchronisation. On a drifting frequency a UPS may refuse to transfer to bypass.
  • Alternator excitation. PMG or auxiliary-winding excitation copes better with distorted current.

5. Walk-in and hold-off

Modern UPS have no inrush at start-up: they ramp up over an adjustable "walk-in" time, and may add a "hold-off" delay so several UPS start in turn. During these intervals the rectifier does not fully supply the load, so the battery may keep discharging, and battery charging is sometimes inhibited too. The battery must therefore cover the genset start, the transfer and the walk-in (see UPS batteries).

6. Acceptance test

  1. Load the UPS realistically (with a load bank if needed).
  2. Simulate a mains failure and confirm the UPS goes to battery.
  3. Check genset start, transfer and gradual load pick-up.
  4. Record genset voltage, frequency and current at each stage.
  5. Restore the mains and confirm a clean retransfer.
  6. Repeat yearly and after any change to the UPS, genset or controls.

Where it falls short

  • The margins are general rules and manufacturer accounts; the real factor comes from the UPS maker for your model.
  • The 40 kW example is illustrative: take real recharge and efficiency from the datasheet.
  • We did not cover paralleled gensets feeding a UPS — see parallel operation.

What to request

  1. UPS input power at full load including recharge, input power factor and THDi.
  2. Input voltage and frequency window and the permitted rate of frequency change.
  3. Walk-in and hold-off settings.
  4. Written compatibility confirmation from both manufacturers.
  5. The list of other loads on the genset (air conditioning, lighting).

FAQ

Can I size the genset from the UPS output rating?

No. Input power is higher: recharge adds to losses, and rectifier harmonics heat the alternator. A genset sized on output often hunts or trips the first time it takes the UPS.

Why does the UPS not accept genset power?

Most often the genset frequency or voltage is outside the UPS input window, or the genset has not settled yet. The UPS stays on battery until it does.

What margin does a modern UPS need?

For a UPS with an IGBT rectifier and PFC the margin can be much smaller than for older thyristor types, down to about 1:1 to input power plus recharge — but only with the maker's written confirmation.